Construction Sovetsky Soyuz-class battleship




1 construction

1.1 sovetsky soyuz
1.2 sovetskaya ukraina
1.3 sovetskaya rossiya
1.4 sovetskaya belorussiya





construction

the august 1938 shipbuilding plan envisioned total of 15 project 23-class battleships, , grandiose scheme revised downward 14 ships in august 1939 plan. 8 of these laid down before 1942 , remaining 6 before 1947. however, 4 laid down before outbreak of world war ii forced soviets reassess ambitious plans. on 19 october 1940 order issued, signed stalin , molotov, no new battleships laid down in order concentrate on smaller ships building (and also, probably, because more resources required army), 1 ship scrapped, , priority should given 1 of 3 remaining battleships.


the soviet shipbuilding , related industries proved incapable of supporting construction of many large ships @ same time. largest warships built in soviet union prior 1938 8,000-metric-ton (7,874-long-ton) kirov-class cruisers, , had suffered number of production problems, soviet leadership appeared ignore difficulties encountered in construction of kirov class when ordering 14 more ambitious ships. construction of 2 more ships planned leningrad , nikolayev had move brand-new shipyard nr. 402 in molotovsk because existing shipyards not expanded handle many large ships. components these 2 ships had manufactured @ leningrad , shipped via white sea – baltic canal molotovsk. also, turret shop @ nikolaev proved poorly equipped assemble 406 mm mountings , propeller shafts had ordered in 1940 germany , netherlands domestic plants overburdened orders. shipbuilding steel proved in short supply in 1940, , number of batches rejected because did not meet specifications. armor plate production more problematic 1,800 metric tons (1,772 long tons) of anticipated 10,000 metric tons (9,842 long tons) delivered in 1939, , more half of rejected. furthermore, armor plants proved incapable of making cemented plates on 230 mm, , inferior face-hardened plates had substitute thicknesses on 200 millimeters (8 in).


machinery problems delay ships past intended delivery dates of 1943–44. 3 turbines delivered brown boveri in 1939 arkhangelsk sovetskaya rossiya, kharkhovskii turbogenerator works never completed single turbine before german invasion in june 1941. prototype boiler supposed have been built ashore evaluation, not completed until 1941, further complicated production plan.


construction of 3 ships ordered halted on 10 july 1941, , sovetsky soyuz placed long-term conservation advanced ship. however, 3 officially stricken navy list on 10 september 1941.


sovetsky soyuz

german reconnaissance picture of sovetsky soyuz taken in june 1942


sovetsky soyuz (russian: Советский Союз—soviet union) formally laid down 15 july 1938 in shipyard nr. 189 (ordzhonikidze) in leningrad, although evidence suggests construction began in january 1939 after slipway completed, necessary cranes in place, , working drawings had been completed. when war began estimated 21.19% complete, 15,818 metric tons (15,568 long tons) of steel assembled on slip. lightly damaged german air attacks , bombardments, and, material had been used during siege of leningrad, estimated 19.5% complete after end of war. thought given completing her, opposed regarded obsolete in light of experience gained during war. stalin s expressed desire see 1 of project 23-class ships completed delayed decision scrap her; ordered on 29 may 1948 , underway april 1949.


sovetskaya ukraina

sovetskaya ukraina (russian: Советская Украина—soviet ukraine) laid down 31 october 1938 @ shipyard nr. 198 (marti south) in nikolayev. when war began 17.98% complete, 13,001 metric tons (12,796 long tons) assembled on slipway. effort made launch hull, little work had been done dredge river @ foot of slipway, , captured on 18 august 1941, although retreating soviet troops damaged hull. germans dismantled 200 feet (61 m) of bow , 100 feet (30 m) of stern use in fortifications. forced evacuate nikolayev on 17 march 1944 , demolished supporting blocks under port side before left, gave list between 5 , 10 degrees , made total loss. ordered scrapped on 27 march 1947.


sovetskaya rossiya

sovetskaya rossiya (russian: Советская Россия—soviet russia) laid down on 22 july 1940 in shipyard nr. 402 in molotovsk. after end of war 0.97% complete, 2,125 metric tons (2,091 long tons) of steel assembled. ordered scrapped on 27 march 1947.


sovetskaya belorussiya

sovetskaya belorussiya (russian: Советская Белоруссия—soviet belorussia) laid down 21 december 1939 @ shipyard nr. 402 in molotovsk, construction suspended in mid-1940 when discovered 70,000 rivets used in hull plating of inferior quality. fact influenced decision cancel on 19 october 1940. material intended construction used construct floating battery defense of leningrad.








Comments

Popular posts from this blog

Memorial Series Board Lutfuddaulah Oriental Research Institute

Weak verbs Proto-Germanic grammar

History Anthrax